Reference Data
BCISM Costbook 2022
Data Kos Pembinaan Malaysia / Malaysian Construction Cost Data · Source: N3C CIDB
2.5 Kadar Unit Utama / Major Unit Rates
Sumber: CIDB Cost Benchmark. Data dari projek di Semenanjung Malaysia
| # | Butiran / Items | Unit | Kadar / Rate (RM) |
|---|---|---|---|
| 1 | Excavation (up to 1.50m deep) | m³ | 18.8 |
| 2 | Hardcore bed, average 150mm thick | m³ | 104.8 |
| 3 | Lean concrete Grade 15 | m³ | 303.9 |
| 4 | Vibrated reinforced concrete Grade 30 | m³ | 324.9 |
| 5 | Mild steel / high tensile bar reinforcement | kg | 4.5 |
| 6 | Sawn formwork to vertical / horizontal surfaces | m² | 39.8 |
| 7 | Half brick wall bedded & jointed in cement mortar | m² | 44.6 |
| 8 | Metal deck roofing: 0.48mm thick c/w all accessories | m² | 64.7 |
| 9 | Aluminium composite cladment window | m² | 360.0 |
| 10 | Timber flush door (hollow core), single leaf excl. ironmongeries | No | 303.9 |
| 11 | One hour fire rated door; single leaf incl. ironmongeries | No | 755.1 |
| 12 | Structural steelwork in column and the like | kg | 12.5 |
| 13 | 20mm thick cement and sand (1:6) plaster to wall | m² | 20.9 |
| 14 | 25mm thick cement and sand (1:3) paving to floor | m² | 18.8 |
| 15 | 300mm x 300mm homogeneous tiles (incl. floor screed) | m² | 83.8 |
| 16 | 4mm thick panflex plaster skim coat | m² | 8.5 |
| 17 | Aluminium strip ceiling | m² | 227.5 |
| 18 | 9mm thick fibrous plaster ceiling | m² | 43.9 |
| 19 | Painting to plastered surfaces; 1 coat sealer + 2 coats emulsion, internally | m² | 8.2 |