Reference Data

BCISM Costbook 2022

Data Kos Pembinaan Malaysia / Malaysian Construction Cost Data · Source: N3C CIDB

2.5 Kadar Unit Utama / Major Unit Rates

Sumber: CIDB Cost Benchmark. Data dari projek di Semenanjung Malaysia

# Butiran / Items Unit Kadar / Rate (RM)
1 Excavation (up to 1.50m deep) 18.8
2 Hardcore bed, average 150mm thick 104.8
3 Lean concrete Grade 15 303.9
4 Vibrated reinforced concrete Grade 30 324.9
5 Mild steel / high tensile bar reinforcement kg 4.5
6 Sawn formwork to vertical / horizontal surfaces 39.8
7 Half brick wall bedded & jointed in cement mortar 44.6
8 Metal deck roofing: 0.48mm thick c/w all accessories 64.7
9 Aluminium composite cladment window 360.0
10 Timber flush door (hollow core), single leaf excl. ironmongeries No 303.9
11 One hour fire rated door; single leaf incl. ironmongeries No 755.1
12 Structural steelwork in column and the like kg 12.5
13 20mm thick cement and sand (1:6) plaster to wall 20.9
14 25mm thick cement and sand (1:3) paving to floor 18.8
15 300mm x 300mm homogeneous tiles (incl. floor screed) 83.8
16 4mm thick panflex plaster skim coat 8.5
17 Aluminium strip ceiling 227.5
18 9mm thick fibrous plaster ceiling 43.9
19 Painting to plastered surfaces; 1 coat sealer + 2 coats emulsion, internally 8.2