# Tred / Trade Keterangan / Description Kadar Output / Output Rate
1 Brickwork Lay only - 100mm thick cement sand brick wall bedded and jointed in cement & sand mortar (1:3) reinforced with 'kennet' reinforcement at every fourth course 1.38 m²/man-hour
2 Concrete Ready mixed concrete including vibrating and trowelling to uniform level in upper floor slab and beam 0.67 m³/man-hour
3 Floor tiling Labour only - 600mm x 300mm floor tiles with cement & sand (1:5) floor base screed, adhesive mortar and pointed in coloured cement to match 1.29 m²/man-hour
4 Formwork Fix and dismantle only - system formwork (aluminium) to sides and soffit of upper floor slab and beam 3.29 m²/man-hour
5 Painting Labour only - prepare and apply one (1) primer coat and two (2) finishing coats internally on surfaces of plastered sides and associated column and beam 10.6 m²/man-hour
6 Paving Labour only - 25mm thick cement and sand (1:3) paving trowelled with a steel float to a smooth and level surface 2.87 m²/man-hour
7 Reinforcement Fabrication and fixing only - 10mm to 32mm rods, BRC AT & AK on upper floor slab and beam 44.8 kg/man-hour
8 Wall plaster Labour only - 20mm thick internal render consist of 2 coats of cement & sand (1:3) finished with steel float including raking out joints of brickwork/or hacking concrete surface for key on sides of brickwork and associated column and beam 1.08 m²/man-hour
9 Wall tiling Labour only - 600mm x 300mm wall tiles with cement & sand (1:3) backing screed, adhesive mortar and pointed in coloured cement to match 0.84 m²/man-hour