Reference Data
BCISM Costbook 2022
Data Kos Pembinaan Malaysia / Malaysian Construction Cost Data · Source: N3C CIDB
3.2 Pemalar Buruh / Labour Constants
Kerja dilakukan setiap jam-pekerja. Sumber: CIDB Labour & Plant Constant 2019
| # | Tred / Trade | Keterangan / Description | Kadar Output / Output Rate |
|---|---|---|---|
| 1 | Brickwork | Lay only - 100mm thick cement sand brick wall bedded and jointed in cement & sand mortar (1:3) reinforced with 'kennet' reinforcement at every fourth course | 1.38 m²/man-hour |
| 2 | Concrete | Ready mixed concrete including vibrating and trowelling to uniform level in upper floor slab and beam | 0.67 m³/man-hour |
| 3 | Floor tiling | Labour only - 600mm x 300mm floor tiles with cement & sand (1:5) floor base screed, adhesive mortar and pointed in coloured cement to match | 1.29 m²/man-hour |
| 4 | Formwork | Fix and dismantle only - system formwork (aluminium) to sides and soffit of upper floor slab and beam | 3.29 m²/man-hour |
| 5 | Painting | Labour only - prepare and apply one (1) primer coat and two (2) finishing coats internally on surfaces of plastered sides and associated column and beam | 10.6 m²/man-hour |
| 6 | Paving | Labour only - 25mm thick cement and sand (1:3) paving trowelled with a steel float to a smooth and level surface | 2.87 m²/man-hour |
| 7 | Reinforcement | Fabrication and fixing only - 10mm to 32mm rods, BRC AT & AK on upper floor slab and beam | 44.8 kg/man-hour |
| 8 | Wall plaster | Labour only - 20mm thick internal render consist of 2 coats of cement & sand (1:3) finished with steel float including raking out joints of brickwork/or hacking concrete surface for key on sides of brickwork and associated column and beam | 1.08 m²/man-hour |
| 9 | Wall tiling | Labour only - 600mm x 300mm wall tiles with cement & sand (1:3) backing screed, adhesive mortar and pointed in coloured cement to match | 0.84 m²/man-hour |