Reference Data

BCISM Costbook 2022

Data Kos Pembinaan Malaysia / Malaysian Construction Cost Data · Source: N3C CIDB

3.3 Pemalar Loji / Plant Constants

Kerja dilakukan setiap jam-loji. Sumber: CIDB Labour & Plant Constant 2019

# Loji / Plant Keterangan / Description Kadar Output / Output Rate
1 Asphalt paver 10-20 tonnes Paving of 50mm to 75mm thick binder/wearing course with asphalt paver 330.88 m²/plant-hour
2 Dump truck 10 wheels Disposal of excavated earth off site to dumping tip within 30km distance with dumping truck 7.96 m³/plant-hour
3 Excavator 20-30 tonnes Excavation to foundation/basement (non adverse ground and weather conditions) 72.15 m³/plant-hour
4 Mobile crane 20-30 tonnes Hoisting of building materials up to 10 storeys high using 20-30 tonne mobile crane operating weight 10.55 tonne/plant-hour
5 Piling driving Drive only 400mm x 600mm precast concrete pile/400mm diameter precast spun pile with jack in piling rig (non adverse ground and weather conditions) 14.29 m/plant-hour
6 Road roller tandem compactor 4,000kg Compaction of 50mm to 75mm thick binder/wearing course with road roller tandem compactor 457.82 m²/plant-hour
7 Tower crane 1-2 tonnes Hoisting of building materials 10-20 storeys height using 1-2 tonne operating weights 12.07 tonne/plant-hour