Reference Data
BCISM Costbook 2022
Data Kos Pembinaan Malaysia / Malaysian Construction Cost Data · Source: N3C CIDB
3.3 Pemalar Loji / Plant Constants
Kerja dilakukan setiap jam-loji. Sumber: CIDB Labour & Plant Constant 2019
| # | Loji / Plant | Keterangan / Description | Kadar Output / Output Rate |
|---|---|---|---|
| 1 | Asphalt paver 10-20 tonnes | Paving of 50mm to 75mm thick binder/wearing course with asphalt paver | 330.88 m²/plant-hour |
| 2 | Dump truck 10 wheels | Disposal of excavated earth off site to dumping tip within 30km distance with dumping truck | 7.96 m³/plant-hour |
| 3 | Excavator 20-30 tonnes | Excavation to foundation/basement (non adverse ground and weather conditions) | 72.15 m³/plant-hour |
| 4 | Mobile crane 20-30 tonnes | Hoisting of building materials up to 10 storeys high using 20-30 tonne mobile crane operating weight | 10.55 tonne/plant-hour |
| 5 | Piling driving | Drive only 400mm x 600mm precast concrete pile/400mm diameter precast spun pile with jack in piling rig (non adverse ground and weather conditions) | 14.29 m/plant-hour |
| 6 | Road roller tandem compactor 4,000kg | Compaction of 50mm to 75mm thick binder/wearing course with road roller tandem compactor | 457.82 m²/plant-hour |
| 7 | Tower crane 1-2 tonnes | Hoisting of building materials 10-20 storeys height using 1-2 tonne operating weights | 12.07 tonne/plant-hour |