Bumbung Kepingan Logam (Metal Deck Roofing)

Section H - Roofing m2 Kuantiti: 14,500.00 SMM: H.1.1 ROF-MTL

Materials

RM 63.80

Labour

RM 9.60

Equipment

RM 0.00

Direct Cost

RM 73.40

OH 10.0%

RM 7.34

Margin 15.0%

RM 12.11

Total Rate

RM 92.85

Materials 86.9% Labour 13.1% Equipment 0.0%

Rate Items

5
# Description Type Unit Qty Waste% Comp Basic Rate Unit Rate Code
1 Kepingan bumbung zincalume 0.47mm (0.47mm zincalume sheet) material m2 1.1000 100% RM 32.00 RM 32.00
2 Purlin C-channel (C-channel purlin) material m2 0.8000 100% RM 15.00 RM 15.00
3 Penebat haba (Thermal insulation) material m2 1.0500 100% RM 12.00 RM 12.00
4 Aksesori & skru (Accessories & screws) material m2 1.0000 100% RM 4.00 RM 4.00
5 Pemasangan (Installation labour) labour m2 0.0800 100% RM 120.00 RM 120.00
Total Direct Cost: RM 73.40

Tambah Item / Add Rate Item

Sejarah Kadar / Rate History

Created Mar 11, 2026 06:25
RM 0.00 RM 92.85