CIDB KPA Build-Up Rate Report
Back to Rate

Build-up Rate

Analisis Kadar Binaan / Rate Build-Up Analysis

Project: Taman Industri Senai Phase 3
Client: Iskandar Investment Bhd
Location: Johor
SMM Ref: H.1.1
Trade Code: ROF-MTL
Date: March 2026
Bumbung Kepingan Logam (Metal Deck Roofing)
No Description Unit Qty Waste % Comp
Factor
Basic
Rate
Unit
Rate
Code
1 Kepingan bumbung zincalume 0.47mm (0.47mm zincalume sheet) m2 1.10 100% RM 32.00 RM 32.00 MB
2 Purlin C-channel (C-channel purlin) m2 0.80 100% RM 15.00 RM 15.00 MB
3 Penebat haba (Thermal insulation) m2 1.05 100% RM 12.00 RM 12.00 MB
4 Aksesori & skru (Accessories & screws) m2 1.00 100% RM 4.00 RM 4.00 MB
5 Pemasangan (Installation labour) m2 0.08 100% RM 120.00 RM 120.00 Lab
Materials Subtotal: RM 63.80
Labour Subtotal: RM 9.60
Jumlah Kos Langsung / Direct Cost: RM 73.40
Kos Bahan / Material Cost RM 63.80
Kos Buruh / Labour Cost RM 9.60
Jumlah Kos Langsung / Direct Cost RM 73.40
Overhed / Overhead (10.0%) RM 7.34
Keuntungan / Profit Margin (15.0%) RM 12.11
KADAR SEUNIT / UNIT RATE (m2) RM 92.85
Disediakan Oleh
Prepared By
Disemak Oleh
Checked By
Diluluskan Oleh
Approved By