Parit Konkrit Bertetulang (RC Box Culvert)

Section T - Drainage & External Works m Kuantiti: 3,200.00 SMM: T.2.1 DRN-CUL

Materials

RM 2,000.00

Labour

RM 170.00

Equipment

RM 84.00

Direct Cost

RM 2,254.00

OH 12.0%

RM 270.48

Margin 15.0%

RM 378.67

Total Rate

RM 2,903.15

Materials 88.7% Labour 7.5% Equipment 3.7%

Rate Items

6
# Description Type Unit Qty Rate Amount
1 Konkrit Gred 30 (Grade 30 concrete) material m 2.5000 RM 240.00 RM 600.00
2 Tetulang keluli (Steel reinforcement) material m 0.3500 RM 3,200.00 RM 1,120.00
3 Acuan (Formwork) material m 8.0000 RM 35.00 RM 280.00
4 Galian (Excavation) equipment m 4.0000 RM 15.00 RM 60.00
5 Kambus balik (Backfill) equipment m 2.0000 RM 12.00 RM 24.00
6 Buruh (Labour) labour m 2.0000 RM 85.00 RM 170.00
Total Direct Cost: RM 2,254.00

Tambah Item / Add Rate Item

Sejarah Kadar / Rate History

Created Mar 11, 2026 06:25
RM 0.00 RM 2,903.15