Parit Konkrit Bertetulang (RC Box Culvert)
Section T - Drainage & External Works
m
Kuantiti: 3,200.00
SMM: T.2.1
DRN-CUL
Materials
RM 2,000.00
Labour
RM 170.00
Equipment
RM 84.00
Direct Cost
RM 2,254.00
OH 12.0%
RM 270.48
Margin 15.0%
RM 378.67
Total Rate
RM 2,903.15
Materials 88.7%
Labour 7.5%
Equipment 3.7%
Rate Items
6Tambah Item / Add Rate Item
Sejarah Kadar / Rate History
Created
Mar 11, 2026 06:25
RM 0.00
RM 2,903.15