Galian Tanah Biasa (Ordinary Earth Excavation)

Section C - Ground Work & Earthworks m3 Kuantiti: 185,000.00 SMM: C.1.1 EXC-ORD

Materials

RM 0.00

Labour

RM 1.40

Equipment

RM 22.40

Direct Cost

RM 23.80

OH 8.0%

RM 1.90

Margin 12.0%

RM 3.08

Total Rate

RM 28.79

Materials 0.0% Labour 5.9% Equipment 94.1%

Rate Items

3
# Description Type Unit Qty Rate Amount
1 Galian jentera (Machine excavation) equipment m3 1.0000 RM 8.00 RM 8.00
2 Buang ke tapak pelupusan (Disposal to dump site) equipment m3 1.2000 RM 12.00 RM 14.40
3 Pekerja (Labour) labour m3 0.0200 RM 70.00 RM 1.40
Total Direct Cost: RM 23.80

Tambah Item / Add Rate Item

Sejarah Kadar / Rate History

Created Mar 11, 2026 06:25
RM 0.00 RM 28.79