Galian Tanah Biasa (Ordinary Earth Excavation)
Section C - Ground Work & Earthworks
m3
Kuantiti: 185,000.00
SMM: C.1.1
EXC-ORD
Materials
RM 0.00
Labour
RM 1.40
Equipment
RM 22.40
Direct Cost
RM 23.80
OH 8.0%
RM 1.90
Margin 12.0%
RM 3.08
Total Rate
RM 28.79
Materials 0.0%
Labour 5.9%
Equipment 94.1%
Rate Items
3Tambah Item / Add Rate Item
Sejarah Kadar / Rate History
Created
Mar 11, 2026 06:25
RM 0.00