Saliran & Longkang (Drainage & Drains)

Section T - Drainage & External Works m Kuantiti: 2,800.00 SMM: T.1.1 DRN-PP

Materials

RM 55.25

Labour

RM 40.00

Equipment

RM 0.00

Direct Cost

RM 95.25

OH 10.0%

RM 9.53

Margin 15.0%

RM 15.72

Total Rate

RM 120.49

Materials 58.0% Labour 42.0% Equipment 0.0%

Rate Items

4
# Description Type Unit Qty Waste% Comp Basic Rate Unit Rate Code
1 Paip HDPE 200mm (200mm HDPE pipe) material m 1.0500 100% RM 45.00 RM 45.00
2 Galian & kambus balik (Excavation & backfill) labour m 0.8000 100% RM 35.00 RM 35.00
3 Hamparan pasir (Sand bedding) material m 0.1000 100% RM 80.00 RM 80.00
4 Pekerja paip (Pipe layer) labour m 0.1200 100% RM 100.00 RM 100.00
Total Direct Cost: RM 95.25

Tambah Item / Add Rate Item

Sejarah Kadar / Rate History

Created Mar 11, 2026 06:25
RM 0.00 RM 120.49