Saliran & Longkang (Drainage & Drains)
Section T - Drainage & External Works
m
Kuantiti: 2,800.00
SMM: T.1.1
DRN-PP
Materials
RM 55.25
Labour
RM 40.00
Equipment
RM 0.00
Direct Cost
RM 95.25
OH 10.0%
RM 9.53
Margin 15.0%
RM 15.72
Total Rate
RM 120.49
Materials 58.0%
Labour 42.0%
Equipment 0.0%
Rate Items
4Tambah Item / Add Rate Item
Sejarah Kadar / Rate History
Created
Mar 11, 2026 06:25
RM 0.00
RM 120.49