CIDB KPA Project Report — Menara Laksamana KL
Back to Project

Build-up Rate Analysis

Analisis Kadar Binaan Projek / Project Rate Build-Up Report

Project:Menara Laksamana KL
Client:UEM Sunrise Bhd
Location:Wilayah Persekutuan Kuala Lumpur
CIDB Reg:CIDB-KL-2026-001248
Total Rates:8
Date:March 2026
GENERAL
Acuan Papan Lapis Lantai (Plywood Slab Formwork) Unit: m2 · Qty: 52000.00
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
1 Papan lapis 18mm (18mm plywood) m2 0.35 100% RM 45.00 RM 45.00 MA
2 Kayu sokongan (Timber support/props) m2 0.15 100% RM 35.00 RM 35.00 MA
3 Paku & aksesori (Nails & accessories) m2 1.00 100% RM 2.50 RM 2.50 MA
4 Tukang kayu (Carpenter) m2 0.12 100% RM 130.00 RM 130.00 LA
5 Pekerja am (General worker) m2 0.08 100% RM 70.00 RM 70.00 LA
Kos Langsung / Direct Cost: RM 44.70
+ OH (10.0%) + Margin (15.0%): RM 11.85
KADAR / RATE per m2: RM 56.55
Cat Emulsi Dalaman 2 Lapis (Internal 2 Coats Emulsion Paint) Unit: m2 · Qty: 85000.00
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
6 Sealer/primer (Primer/sealer) m2 0.12 100% RM 18.00 RM 18.00 MA
7 Cat emulsi (Emulsion paint) m2 0.25 100% RM 22.00 RM 22.00 MA
8 Tukang cat (Painter) m2 0.06 100% RM 110.00 RM 110.00 LA
9 Kertas pasir & alatan (Sandpaper & tools) m2 1.00 100% RM 1.20 RM 1.20 MA
Kos Langsung / Direct Cost: RM 15.46
+ OH (8.0%) + Margin (12.0%): RM 3.24
KADAR / RATE per m2: RM 18.70
Dinding Blok Konkrit 150mm (150mm Concrete Block Wall) Unit: m2 · Qty: 28000.00
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
10 Blok konkrit 150mm (150mm concrete block) m2 12.50 100% RM 2.80 RM 2.80 MA
11 Mortar simen 1:4 (Cement mortar 1:4) m2 0.02 100% RM 350.00 RM 350.00 MA
12 Tukang batu (Mason) m2 0.22 100% RM 120.00 RM 120.00 LA
13 Pekerja am (Helper) m2 0.22 100% RM 70.00 RM 70.00 LA
14 Perancah (Scaffolding) m2 1.00 100% RM 3.50 RM 3.50 EQ
Kos Langsung / Direct Cost: RM 86.60
+ OH (10.0%) + Margin (12.0%): RM 20.09
KADAR / RATE per m2: RM 106.69
Jubin Homogeneous 600x600mm (600x600mm Homogeneous Floor Tiles) Unit: m2 · Qty: 32000.00
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
15 Jubin homogeneous 600x600 (600x600 homogeneous tiles) m2 1.10 100% RM 38.00 RM 38.00 MA
16 Perekat jubin (Tile adhesive) m2 0.50 100% RM 14.00 RM 14.00 MA
17 Grout (Grout) m2 0.30 100% RM 8.00 RM 8.00 MA
18 Tukang jubin mahir (Skilled tiler) m2 0.25 100% RM 140.00 RM 140.00 LA
19 Pekerja am (Helper) m2 0.12 100% RM 70.00 RM 70.00 LA
Kos Langsung / Direct Cost: RM 94.60
+ OH (10.0%) + Margin (15.0%): RM 25.07
KADAR / RATE per m2: RM 119.67
Kalis Air Bilik Air (Bathroom Waterproofing) Unit: m2 · Qty: 4500.00
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
20 Membran kalis air (Waterproofing membrane) m2 1.10 100% RM 18.00 RM 18.00 MA
21 Primer (Primer coat) m2 1.00 100% RM 5.00 RM 5.00 MA
22 Lapisan pelindung (Protection screed) m2 1.00 100% RM 8.00 RM 8.00 MA
23 Tukang kalis air (Waterproofing applicator) m2 0.15 100% RM 130.00 RM 130.00 LA
Kos Langsung / Direct Cost: RM 52.30
+ OH (10.0%) + Margin (15.0%): RM 13.86
KADAR / RATE per m2: RM 66.16
Konkrit Gred 40 Siap Tuang (Grade 40 Concrete Supply & Pour) Unit: m3 · Qty: 14500.00
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
24 Konkrit sedia campur Gred 40 (Ready-mix concrete Grade 40) m3 1.05 100% RM 280.00 RM 280.00 MA
25 Pam konkrit (Concrete pump) m3 1.00 100% RM 18.00 RM 18.00 EQ
26 Kumpulan pekerja konkrit 6 orang (Concrete gang) m3 0.50 100% RM 85.00 RM 85.00 LA
27 Bahan pengawetan (Curing compound) m3 0.30 100% RM 12.00 RM 12.00 MA
28 Ujian kiub & QC (Cube test & QC) m3 1.00 100% RM 6.00 RM 6.00 OT
Kos Langsung / Direct Cost: RM 364.10
+ OH (10.0%) + Margin (15.0%): RM 96.49
KADAR / RATE per m3: RM 460.59
Plaster Simen 20mm (20mm Cement Sand Plaster) Unit: m2 · Qty: 55000.00
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
29 Simen (Cement) m2 0.30 100% RM 22.00 RM 22.00 MA
30 Pasir (Sand) m2 0.01 100% RM 85.00 RM 85.00 MA
31 Tukang plaster (Plasterer) m2 0.15 100% RM 120.00 RM 120.00 LA
32 Pekerja am (Helper) m2 0.08 100% RM 70.00 RM 70.00 LA
Kos Langsung / Direct Cost: RM 31.22
+ OH (10.0%) + Margin (12.0%): RM 7.24
KADAR / RATE per m2: RM 38.46
Tetulang Keluli T12-T32 Gred 500 (Steel Reinforcement T12-T32 Grade 500) Unit: ton · Qty: 3800.00
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
33 Bar keluli Gred 500 (Grade 500 steel bar) ton 1.03 100% RM 2,650.00 RM 2,650.00 MA
34 Potong & bengkok (Cutting & bending) ton 1.00 100% RM 120.00 RM 120.00 LA
35 Ikat & pasang (Fixing crew) ton 1.00 100% RM 280.00 RM 280.00 LA
36 Dawai pengikat & spacer (Tying wire & spacers) ton 1.00 100% RM 35.00 RM 35.00 MA
37 Kren (Crane usage) ton 0.50 100% RM 65.00 RM 65.00 EQ
Kos Langsung / Direct Cost: RM 3,197.00
+ OH (10.0%) + Margin (15.0%): RM 847.21
KADAR / RATE per ton: RM 4,044.21
Total Rates in Project 8 items
JUMLAH BESAR / GRAND TOTAL RM 35,806,331.16