Project

Menara Laksamana KL

Active

UEM Sunrise Bhd · Wilayah Persekutuan Kuala Lumpur · CIDB CIDB-KL-2026-001248

Bajet / Budget

RM 185,000,000.00

Anggaran Kos / Est. Cost

RM 35,806,331.16

Levi CIDB (0.125%)

RM 44,757.91

Jumlah + Levi / Total

RM 35,851,089.07

Varians / Variance

RM 149,148,910.93

Penggunaan / Used

19.38%

Pecahan Kos / Cost Breakdown

83%

RM 3,227.38

Bahan / Materials

15%

RM 598.60

Buruh / Labour

2%

RM 60.00

Jentera / Equipment

Kadar Binaan / Build-Up Rates

8
Description Category Unit Qty Rate Amount Status Actions
Konkrit Gred 40 Siap Tuang (Grade 40 Concr... In-Situ Concrete Works m3 14,500.00 RM 460.59 RM 6,678,504.25 Reviewed Edit Delete
Acuan Papan Lapis Lantai (Plywood Slab For... Formwork m2 52,000.00 RM 56.55 RM 2,940,366.00 Approved Edit Delete
Tetulang Keluli T12-T32 Gred 500 (Steel Re... Reinforcement ton 3,800.00 RM 4,044.21 RM 15,367,979.00 Reviewed Edit Delete
Dinding Blok Konkrit 150mm (150mm Concrete... Brickwork & Blockwork m2 28,000.00 RM 106.69 RM 2,987,353.60 Reviewed Edit Delete
Plaster Simen 20mm (20mm Cement Sand Plaster) Plastering & Rendering m2 55,000.00 RM 38.46 RM 2,115,467.20 Approved Edit Delete
Jubin Homogeneous 600x600mm (600x600mm Hom... Floor & Wall Tiling m2 32,000.00 RM 119.67 RM 3,829,408.00 Reviewed Edit Delete
Cat Emulsi Dalaman 2 Lapis (Internal 2 Coa... Painting & Decorating m2 85,000.00 RM 18.70 RM 1,589,535.36 Reviewed Edit Delete
Kalis Air Bilik Air (Bathroom Waterproofing) Waterproofing m2 4,500.00 RM 66.16 RM 297,717.75 Reviewed Edit Delete
Grand Total: RM 35,806,331.16