CIDB KPA Project Report — KPA Sample Project - Brickwall
Back to Project

Build-up Rate Analysis

Analisis Kadar Binaan Projek / Project Rate Build-Up Report

Project:KPA Sample Project - Brickwall
Client:CIDB Malaysia
Location:Selangor
CIDB Reg:CIDB-KPA-2024
Total Rates:4
Date:April 2026
BRICKWALL
115mm Thick brick wall in common bricks in gauge mortar (1:3) in sand mesh reinforcement at every fourth course Unit: m2 · Qty: 1.00
219mm (L) x 66mm (H) x 99mm (W)
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
1 Clay bricks nos 57.00 105% RM 0.32 RM 0.34 MB
2 Kumat (wire mesh) m2 3.33 105% RM 0.13 RM 0.14 CM
3 Cement kg 309.00 105% 1.25 RM 0.29 RM 0.38 M1
4 Fine Sand m3 0.75 105% 1.25 RM 51.06 RM 67.02 CW
5 Water nos 27.00 105% RM 0.00 RM 0.00 CM
6 Labour nos 57.00 100% RM 0.15 RM 0.15 Lab
Kos Langsung / Direct Cost: RM 196.03
+ OH (10.0%) + Margin (15.0%): RM 51.95
KADAR / RATE per m2: RM 247.98
115mm Thick brick wall in common bricks in gauge mortar (1:6) in sand mesh reinforcement at every fourth course Unit: m2 · Qty: 1.00
219mm (L) x 66mm (H) x 99mm (W)
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
7 Clay bricks nos 57.00 105% RM 0.32 RM 0.34 MB
8 Kumat (wire mesh) m2 3.33 105% RM 0.13 RM 0.14 CM
9 Cement kg 206.14 105% 1.25 RM 0.29 RM 0.38 CM
10 Fine Sand m3 0.86 105% 1.25 RM 51.08 RM 67.04 CW
11 Water nos 27.00 105% RM 0.00 RM 0.00 CM
12 Labour nos 57.00 100% RM 0.15 RM 0.15 Lab
Kos Langsung / Direct Cost: RM 164.28
+ OH (10.0%) + Margin (15.0%): RM 43.53
KADAR / RATE per m2: RM 207.81
220mm Thick brick wall in common bricks in gauge mortar (1:3) in sand mesh reinforcement at every fourth course Unit: m2 · Qty: 1.00
219mm (L) x 66mm (H) x 99mm (W)
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
13 Clay bricks nos 114.00 105% RM 0.32 RM 0.34 MB
14 Kumat (wire mesh) m2 6.66 105% RM 0.13 RM 0.14 CM
15 Cement kg 710.00 105% 1.25 RM 0.29 RM 0.38 M1
16 Fine Sand m3 1.50 105% 1.25 RM 51.06 RM 67.02 CW
17 Water nos 54.00 105% RM 0.00 RM 0.00 CM
18 Labour nos 114.00 100% RM 0.15 RM 0.15 Lab
Kos Langsung / Direct Cost: RM 427.08
+ OH (10.0%) + Margin (15.0%): RM 113.18
KADAR / RATE per m2: RM 540.26
230mm Thick brick wall in common bricks in gauge mortar (1:6) in sand mesh reinforcement at every fourth course Unit: m2 · Qty: 1.00
219mm (L) x 66mm (H) x 99mm (W)
No Description Unit Qty Waste Comp Basic Rate Unit Rate Code
19 Clay bricks nos 114.00 105% RM 0.32 RM 0.34 MB
20 Kumat (wire mesh) m2 6.66 105% RM 0.13 RM 0.14 CM
21 Cement kg 410.28 105% 1.25 RM 0.29 RM 0.38 CM
22 Fine Sand m3 1.72 105% 1.25 RM 51.08 RM 67.04 CW
23 Water nos 54.00 105% RM 0.00 RM 0.00 CM
24 Labour nos 114.00 100% RM 0.15 RM 0.15 Lab
Kos Langsung / Direct Cost: RM 327.79
+ OH (10.0%) + Margin (15.0%): RM 86.86
KADAR / RATE per m2: RM 414.65
Total Rates in Project 4 items
JUMLAH BESAR / GRAND TOTAL RM 1,410.70
Disediakan Oleh
Prepared By
Disemak Oleh
Checked By
Diluluskan Oleh
Approved By