220mm Thick brick wall in common bricks in gauge mortar (1:3) in sand mesh reinforcement at every fourth course

Section G - Brickwork & Blockwork > Clay Brickwork m2 Kuantiti: 1.00 SMM: G1.2.2 BRW/04

Materials

RM 319.84

Labour

RM 17.10

Equipment

RM 0.00

Direct Cost

RM 336.94

OH 10.0%

RM 33.69

Margin 15.0%

RM 55.60

Total Rate

RM 426.23

Materials 94.9% Labour 5.1% Equipment 0.0%

Rate Items

6
# Description Type Unit Qty Waste% Comp Basic Rate Unit Rate Code
1 Clay bricks material nos 114.0000 105% RM 0.32 RM 0.34 MB
2 Kumat (wire mesh) material m2 6.6600 105% RM 0.13 RM 0.14 CM
3 Cement material kg 710.0000 105% 1.25 RM 0.29 RM 0.38 M1
4 Fine Sand material m3 1.5000 105% 1.25 RM 51.06 RM 67.02 CW
5 Water material nos 54.0000 105% RM 0.00 RM 0.00 CM
6 Labour labour nos 114.0000 100% RM 0.15 RM 0.15 Lab
Total Direct Cost: RM 336.94

Tambah Item / Add Rate Item

Sejarah Kadar / Rate History

Created Mar 11, 2026 09:51
RM 0.00 RM 426.23