115mm Thick brick wall in common bricks in gauge mortar (1:3) in sand mesh reinforcement at every fourth course

Section G - Brickwork & Blockwork > Clay Brickwork m2 Kuantiti: 1.00 SMM: G1.2.1 BRW/03

Materials

RM 146.58

Labour

RM 8.55

Equipment

RM 0.00

Direct Cost

RM 155.13

OH 10.0%

RM 15.51

Margin 15.0%

RM 25.60

Total Rate

RM 196.24

Materials 94.5% Labour 5.5% Equipment 0.0%

Rate Items

6
# Description Type Unit Qty Waste% Comp Basic Rate Unit Rate Code
1 Clay bricks material nos 57.0000 105% RM 0.32 RM 0.34 MB
2 Kumat (wire mesh) material m2 3.3300 105% RM 0.13 RM 0.14 CM
3 Cement material kg 309.0000 105% 1.25 RM 0.29 RM 0.38 M1
4 Fine Sand material m3 0.7500 105% 1.25 RM 51.06 RM 67.02 CW
5 Water material nos 27.0000 105% RM 0.00 RM 0.00 CM
6 Labour labour nos 57.0000 100% RM 0.15 RM 0.15 Lab
Total Direct Cost: RM 155.13

Tambah Item / Add Rate Item

Sejarah Kadar / Rate History

Created Mar 11, 2026 09:51
RM 0.00 RM 196.24