CIDB KPA Build-Up Rate Report
Back to Rate

Build-up Rate

Analisis Kadar Binaan / Rate Build-Up Analysis

Project: KPA Sample Project - Brickwall
Client: CIDB Malaysia
Location: Selangor
SMM Ref: G1.1.2
Trade Code: BRW/02
Date: April 2026
BRICKWALL
230mm Thick brick wall in common bricks in gauge mortar (1:6) in sand mesh reinforcement at every fourth course
219mm (L) x 66mm (H) x 99mm (W)
No Description Unit Qty Waste % Comp
Factor
Basic
Rate
Unit
Rate
Code
1 Clay bricks nos 114.00 105% RM 0.32 RM 0.34 MB
2 Kumat (wire mesh) m2 6.66 105% RM 0.13 RM 0.14 CM
3 Cement kg 410.28 105% 1.25 RM 0.29 RM 0.38 CM
4 Fine Sand m3 1.72 105% 1.25 RM 51.08 RM 67.04 CW
5 Water nos 54.00 105% RM 0.00 RM 0.00 CM
6 Labour nos 114.00 100% RM 0.15 RM 0.15 Lab
Materials Subtotal: RM 310.69
Labour Subtotal: RM 17.10
Jumlah Kos Langsung / Direct Cost: RM 327.79
Kos Bahan / Material Cost RM 310.69
Kos Buruh / Labour Cost RM 17.10
Jumlah Kos Langsung / Direct Cost RM 327.79
Overhed / Overhead (10.0%) RM 32.78
Keuntungan / Profit Margin (15.0%) RM 54.09
KADAR SEUNIT / UNIT RATE (m2) RM 414.65
Disediakan Oleh
Prepared By
Disemak Oleh
Checked By
Diluluskan Oleh
Approved By