115mm Thick brick wall in common bricks in gauge mortar (1:6) in sand mesh reinforcement at every fourth course

Section G - Brickwork & Blockwork > Clay Brickwork m2 Kuantiti: 1.00 SMM: G1.1.1 BRW/01

Materials

RM 122.38

Labour

RM 8.55

Equipment

RM 0.00

Direct Cost

RM 130.93

OH 10.0%

RM 13.09

Margin 15.0%

RM 21.60

Total Rate

RM 165.63

Materials 93.5% Labour 6.5% Equipment 0.0%

Rate Items

6
# Description Type Unit Qty Waste% Comp Basic Rate Unit Rate Code
1 Clay bricks material nos 57.0000 105% RM 0.32 RM 0.34 MB
2 Kumat (wire mesh) material m2 3.3300 105% RM 0.13 RM 0.14 CM
3 Cement material kg 206.1400 105% 1.25 RM 0.29 RM 0.38 CM
4 Fine Sand material m3 0.8600 105% 1.25 RM 51.08 RM 67.04 CW
5 Water material nos 27.0000 105% RM 0.00 RM 0.00 CM
6 Labour labour nos 57.0000 100% RM 0.15 RM 0.15 Lab
Total Direct Cost: RM 130.93