CIDB KPA Build-Up Rate Report
Back to Rate

Build-up Rate

Analisis Kadar Binaan / Rate Build-Up Analysis

Project: Sekolah Menengah Kebangsaan Baru Cyberjaya
Client: Kementerian Pendidikan Malaysia (KPM)
Location: Selangor
SMM Ref: D.1.1
Trade Code: CON-G35
Date: March 2026
Konkrit Gred 35 Struktur (Grade 35 Structural Concrete)
No Description Unit Qty Waste % Comp
Factor
Basic
Rate
Unit
Rate
Code
1 Konkrit sedia campur Gred 35 (Ready-mix Grade 35) m3 1.05 100% RM 260.00 RM 260.00 MB
2 Kumpulan konkrit (Concrete gang) m3 0.50 100% RM 82.00 RM 82.00 Lab
3 Pam konkrit (Concrete pump) m3 1.00 100% RM 16.00 RM 16.00 Eq
4 Ujian & QC (Testing & QC) m3 1.00 100% RM 5.50 RM 5.50 Eq
Materials Subtotal: RM 273.00
Labour Subtotal: RM 41.00
Equipment Subtotal: RM 21.50
Jumlah Kos Langsung / Direct Cost: RM 335.50
Kos Bahan / Material Cost RM 273.00
Kos Buruh / Labour Cost RM 41.00
Kos Peralatan / Equipment Cost RM 21.50
Jumlah Kos Langsung / Direct Cost RM 335.50
Overhed / Overhead (10.0%) RM 33.55
Keuntungan / Profit Margin (12.0%) RM 44.29
KADAR SEUNIT / UNIT RATE (m3) RM 413.34
Disediakan Oleh
Prepared By
Disemak Oleh
Checked By
Diluluskan Oleh
Approved By