CIDB KPA Build-Up Rate Report
Back to Rate

Build-up Rate

Analisis Kadar Binaan / Rate Build-Up Analysis

Project: Taman Industri Senai Phase 3
Client: Iskandar Investment Bhd
Location: Johor
SMM Ref: D.1.2
Trade Code: CON-G30
Date: March 2026
Konkrit Gred 30 Tapak (Grade 30 Foundation Concrete)
No Description Unit Qty Waste % Comp
Factor
Basic
Rate
Unit
Rate
Code
1 Konkrit sedia campur Gred 30 (Ready-mix Grade 30) m3 1.05 100% RM 240.00 RM 240.00 MB
2 Kumpulan konkrit (Concrete gang) m3 0.50 100% RM 80.00 RM 80.00 Lab
3 Pam konkrit (Concrete pump) m3 1.00 100% RM 15.00 RM 15.00 Eq
4 Ujian kiub (Cube test) m3 1.00 100% RM 5.00 RM 5.00 Eq
Materials Subtotal: RM 252.00
Labour Subtotal: RM 40.00
Equipment Subtotal: RM 20.00
Jumlah Kos Langsung / Direct Cost: RM 312.00
Kos Bahan / Material Cost RM 252.00
Kos Buruh / Labour Cost RM 40.00
Kos Peralatan / Equipment Cost RM 20.00
Jumlah Kos Langsung / Direct Cost RM 312.00
Overhed / Overhead (12.0%) RM 37.44
Keuntungan / Profit Margin (15.0%) RM 52.42
KADAR SEUNIT / UNIT RATE (m3) RM 401.86
Disediakan Oleh
Prepared By
Disemak Oleh
Checked By
Diluluskan Oleh
Approved By