CIDB KPA Build-Up Rate Report
Back to Rate

Build-up Rate

Analisis Kadar Binaan / Rate Build-Up Analysis

Project: Menara Laksamana KL
Client: UEM Sunrise Bhd
Location: Wilayah Persekutuan Kuala Lumpur
SMM Ref: S.1.1
Trade Code: WPF-BTH
Date: March 2026
Kalis Air Bilik Air (Bathroom Waterproofing)
No Description Unit Qty Waste % Comp
Factor
Basic
Rate
Unit
Rate
Code
1 Membran kalis air (Waterproofing membrane) m2 1.10 100% RM 18.00 RM 18.00 MB
2 Primer (Primer coat) m2 1.00 100% RM 5.00 RM 5.00 MB
3 Lapisan pelindung (Protection screed) m2 1.00 100% RM 8.00 RM 8.00 MB
4 Tukang kalis air (Waterproofing applicator) m2 0.15 100% RM 130.00 RM 130.00 Lab
Materials Subtotal: RM 32.80
Labour Subtotal: RM 19.50
Jumlah Kos Langsung / Direct Cost: RM 52.30
Kos Bahan / Material Cost RM 32.80
Kos Buruh / Labour Cost RM 19.50
Jumlah Kos Langsung / Direct Cost RM 52.30
Overhed / Overhead (10.0%) RM 5.23
Keuntungan / Profit Margin (15.0%) RM 8.63
KADAR SEUNIT / UNIT RATE (m2) RM 66.16