CIDB KPA Build-Up Rate Report
Back to Rate

Build-up Rate

Analisis Kadar Binaan / Rate Build-Up Analysis

Project: Menara Laksamana KL
Client: UEM Sunrise Bhd
Location: Wilayah Persekutuan Kuala Lumpur
SMM Ref: P.1.1
Trade Code: TIL-HOM
Date: March 2026
Jubin Homogeneous 600x600mm (600x600mm Homogeneous Floor Tiles)
No Description Unit Qty Waste % Comp
Factor
Basic
Rate
Unit
Rate
Code
1 Jubin homogeneous 600x600 (600x600 homogeneous tiles) m2 1.10 100% RM 38.00 RM 38.00 MB
2 Perekat jubin (Tile adhesive) m2 0.50 100% RM 14.00 RM 14.00 MB
3 Grout (Grout) m2 0.30 100% RM 8.00 RM 8.00 MB
4 Tukang jubin mahir (Skilled tiler) m2 0.25 100% RM 140.00 RM 140.00 Lab
5 Pekerja am (Helper) m2 0.12 100% RM 70.00 RM 70.00 Lab
Materials Subtotal: RM 51.20
Labour Subtotal: RM 43.40
Jumlah Kos Langsung / Direct Cost: RM 94.60
Kos Bahan / Material Cost RM 51.20
Kos Buruh / Labour Cost RM 43.40
Jumlah Kos Langsung / Direct Cost RM 94.60
Overhed / Overhead (10.0%) RM 9.46
Keuntungan / Profit Margin (15.0%) RM 15.61
KADAR SEUNIT / UNIT RATE (m2) RM 119.67
Disediakan Oleh
Prepared By
Disemak Oleh
Checked By
Diluluskan Oleh
Approved By