CIDB KPA Build-Up Rate Report
Back to Rate

Build-up Rate

Analisis Kadar Binaan / Rate Build-Up Analysis

Project: Menara Laksamana KL
Client: UEM Sunrise Bhd
Location: Wilayah Persekutuan Kuala Lumpur
SMM Ref: N.1.1
Trade Code: PLS-CS
Date: March 2026
Plaster Simen 20mm (20mm Cement Sand Plaster)
No Description Unit Qty Waste % Comp
Factor
Basic
Rate
Unit
Rate
Code
1 Simen (Cement) m2 0.30 100% RM 22.00 RM 22.00 MB
2 Pasir (Sand) m2 0.01 100% RM 85.00 RM 85.00 MB
3 Tukang plaster (Plasterer) m2 0.15 100% RM 120.00 RM 120.00 Lab
4 Pekerja am (Helper) m2 0.08 100% RM 70.00 RM 70.00 Lab
Materials Subtotal: RM 7.62
Labour Subtotal: RM 23.60
Jumlah Kos Langsung / Direct Cost: RM 31.22
Kos Bahan / Material Cost RM 7.62
Kos Buruh / Labour Cost RM 23.60
Jumlah Kos Langsung / Direct Cost RM 31.22
Overhed / Overhead (10.0%) RM 3.12
Keuntungan / Profit Margin (12.0%) RM 4.12
KADAR SEUNIT / UNIT RATE (m2) RM 38.46
Disediakan Oleh
Prepared By
Disemak Oleh
Checked By
Diluluskan Oleh
Approved By