CIDB KPA Build-Up Rate Report
Back to Rate

Build-up Rate

Analisis Kadar Binaan / Rate Build-Up Analysis

Project: Menara Laksamana KL
Client: UEM Sunrise Bhd
Location: Wilayah Persekutuan Kuala Lumpur
SMM Ref: E.1.1
Trade Code: FWK-SLB
Date: March 2026
Acuan Papan Lapis Lantai (Plywood Slab Formwork)
No Description Unit Qty Waste % Comp
Factor
Basic
Rate
Unit
Rate
Code
1 Papan lapis 18mm (18mm plywood) m2 0.35 100% RM 45.00 RM 45.00 MB
2 Kayu sokongan (Timber support/props) m2 0.15 100% RM 35.00 RM 35.00 MB
3 Paku & aksesori (Nails & accessories) m2 1.00 100% RM 2.50 RM 2.50 MB
4 Tukang kayu (Carpenter) m2 0.12 100% RM 130.00 RM 130.00 Lab
5 Pekerja am (General worker) m2 0.08 100% RM 70.00 RM 70.00 Lab
Materials Subtotal: RM 23.50
Labour Subtotal: RM 21.20
Jumlah Kos Langsung / Direct Cost: RM 44.70
Kos Bahan / Material Cost RM 23.50
Kos Buruh / Labour Cost RM 21.20
Jumlah Kos Langsung / Direct Cost RM 44.70
Overhed / Overhead (10.0%) RM 4.47
Keuntungan / Profit Margin (15.0%) RM 7.38
KADAR SEUNIT / UNIT RATE (m2) RM 56.55
Disediakan Oleh
Prepared By
Disemak Oleh
Checked By
Diluluskan Oleh
Approved By