Kalkulator / VOP

Section 4.4

Variasi Harga / Variation of Price (VOP)

Pengiraan variasi harga bahan antara tarikh anugerah dan tarikh semasa

Input Pengiraan VOP

Kosongkan untuk pengiraan bahan spesifik (reinforcement bar dll)

Panduan Pengiraan VOP / VOP Guide

Contoh 1: Kerja Bangunan

Pemberat bahan = 0.70, BMCI Anugerah = 103.0, BMCI Semasa = 129.5

Nilai kerja siap = RM2,500,000.00

VOP = 0.70 × ((129.5 - 103.0) / 103.0) × 2,500,000 = RM450,242.72

Contoh 2: Bahan Spesifik (Reinforcement)

BMCI Anugerah = 107.1, BMCI Semasa = 140.3

Harga jualan rebar Y10 = RM2,466.67/tonne

VOP = ((140.3 - 107.1) / 107.1) × 2,466.67 = RM764.64/tonne

Sumber: N3C Building Material Cost Index (BMCI)