Section 4.6-4.7
Pengiraan Produktiviti / Productivity Calculator
Anggaran masa diperlukan untuk menyiapkan kerja
Input Pengiraan / Calculation Input
Pemalar Buruh / Labour Constants
Brickwork
1.38 m²/man-hour
Concrete
0.67 m³/man-hour
Floor tiling
1.29 m²/man-hour
Formwork
3.29 m²/man-hour
Painting
10.6 m²/man-hour
Paving
2.87 m²/man-hour
Reinforcement
44.8 kg/man-hour
Wall plaster
1.08 m²/man-hour
Wall tiling
0.84 m²/man-hour
Pemalar Loji / Plant Constants
Asphalt paver 10-20 tonnes
330.88 m²/plant-hour
Dump truck 10 wheels
7.96 m³/plant-hour
Excavator 20-30 tonnes
72.15 m³/plant-hour
Mobile crane 20-30 tonnes
10.55 tonne/plant-hour
Piling driving
14.29 m/plant-hour
Road roller tandem compactor 4,000kg
457.82 m²/plant-hour
Tower crane 1-2 tonnes
12.07 tonne/plant-hour