Kalkulator / Produktiviti

Section 4.6-4.7

Pengiraan Produktiviti / Productivity Calculator

Anggaran masa diperlukan untuk menyiapkan kerja

Input Pengiraan / Calculation Input

Pemalar Buruh / Labour Constants

Brickwork 1.38 m²/man-hour
Concrete 0.67 m³/man-hour
Floor tiling 1.29 m²/man-hour
Formwork 3.29 m²/man-hour
Painting 10.6 m²/man-hour
Paving 2.87 m²/man-hour
Reinforcement 44.8 kg/man-hour
Wall plaster 1.08 m²/man-hour
Wall tiling 0.84 m²/man-hour

Pemalar Loji / Plant Constants

Asphalt paver 10-20 tonnes 330.88 m²/plant-hour
Dump truck 10 wheels 7.96 m³/plant-hour
Excavator 20-30 tonnes 72.15 m³/plant-hour
Mobile crane 20-30 tonnes 10.55 tonne/plant-hour
Piling driving 14.29 m/plant-hour
Road roller tandem compactor 4,000kg 457.82 m²/plant-hour
Tower crane 1-2 tonnes 12.07 tonne/plant-hour