Pengiraan Kadar Binaan / Built-Up Rate Calculator

Kira kadar menggunakan kos bahan, buruh dan jentera dengan pemalar BCISM

Kos Bahan / Material Cost

Kos Buruh / Labour Cost

Kos Jentera / Equipment Cost

Rujukan Upah Buruh / Labour Rates (RM/day)

Barbender 160
Bricklayer 170
Concretor 160
Excavator operator 200
General construction worker 100
IBS precast concrete installer 200
Painter 160
Plasterer 170
Plumber (building & sanitary) 200
Steel structure fabricator 180

Rujukan Jentera / Machinery (RM/day)

Backhoe loader 380.0
Bulldozer 540.0
Dump truck 360.0
Lorry 200.0
Mini hydraulic excavator 370.0
Mobile crane 510.0
Motor grader 750.0
Vibratory compactor 410.0

Pemalar / Constants

Brickwork 1.38 m²/man-hour
Concrete 0.67 m³/man-hour
Floor tiling 1.29 m²/man-hour
Formwork 3.29 m²/man-hour
Painting 10.6 m²/man-hour
Paving 2.87 m²/man-hour
Reinforcement 44.8 kg/man-hour
Wall plaster 1.08 m²/man-hour
Wall tiling 0.84 m²/man-hour
Asphalt paver 10-20 tonnes 330.88 m²/plant-hour
Dump truck 10 wheels 7.96 m³/plant-hour
Excavator 20-30 tonnes 72.15 m³/plant-hour
Mobile crane 20-30 tonnes 10.55 tonne/plant-hour
Piling driving 14.29 m/plant-hour
Road roller tandem compactor 4,000kg 457.82 m²/plant-hour
Tower crane 1-2 tonnes 12.07 tonne/plant-hour